1. Home
  2. Use cases
  3. Execute

Execute · Projects in construction

Which projects are drifting, and which recovery works?

Execute turns the monthly cost ledger and progress report into a P80 cost and finish for every unit, then prices the ways out. A contractor's milestone date is treated as one piece of evidence, not the forecast.

Output: P80 cost and finish for each unit, updated from actuals; recovery options priced in money and previewed before commitment; change orders routed by your authority matrix.

Who it is for

For the people answerable for the finish date

Project controls teams, PMOs, project directors and lenders' engineers. Execute sits above Primavera and SAP; it reads what they export and adds the range they do not give you.

  • Project controls
  • PMO
  • Project directors
  • Lenders' engineers
  • Owner's team

Questions it answers

  1. What will each unit cost and when will it finish, at P50 and at P80?
  2. Is remaining contingency enough for the P80, and what do pending claims do to it?
  3. Which contractor dates are optimistic, and are they moving between reports?
  4. Which unit drives the programme finish, and what does a day of delay cost?
  5. Would a second shift, crew moves or resequencing pay for itself?

What Capibud produces

A monthly review with the range attached

Earned-value measures are the starting point. Capibud blends them with a reference-class prior, simulates the risks that remain and checks the result against crew ceilings and calendar windows.

01

P80 cost and finish

For each unit and the programme, from correlated scenarios, with the chance of finishing within budget authority.

02

A verdict per unit

Proceed, watch, recover or escalate, with the reasons stated in plain terms beside each verdict.

03

Contractor date checks

Reported milestone dates against Capibud's P50 and P80, and how far the reported date moved across recent reports.

04

Contingency coverage

Remaining contingency against the P80 need, with pending change orders simulated at their likelihood of being granted.

05

Priced recovery

Second shifts, crew moves and resequencing priced in money and previewed against shared crew ceilings before anyone commits.

06

Routed change orders

Every change order follows the authority matrix, with maker-checker and cumulative-change rules.

Worked example

Phase 1 of an AI campus, sixteen months in

Illustrative demo — not client data

A synthetic hyperscale campus has six packages and a combined budget authority of $1,185M. At the September data date, CPI is 0.96 and SPI 0.95. Only 42% of 2,000 correlated scenarios finish within authority, and remaining contingency covers 73% of the P80 need.

The data-hall fit-out drives the finish: P80 about six months beyond target, at roughly $520,000 a day. Crews on that package are at 79% of what the work in hand needs, so the first recovery option to price is a second shift.

The same campus, from option choice to construction, is in the data-centre developer case.

Monthly review · September Synthetic workspace · USD
PackageBudgetP80 costP80 finishvs targetVerdict
Shell and core$176M$187MOct 2026Sep 2026Proceed
Long-lead electrical$228M$257MFeb 2027Dec 2026Recover
230 kV substation$106M$120MAug 2027Mar 2027Recover
Cooling plant$150M$177MMar 2027Jan 2027Escalate
Backup generation$96M$98MJan 2027Dec 2026Proceed
Data halls 1–3 fit-out$325M$392MFeb 2028Aug 2027Escalate

Illustrative demo — not client data. Synthetic execution history; one seeded engine run. Budgets are at award; package P80s do not sum to the programme P80.

Contractor dates vs Capibud P80 Days the report is earlier
Utility line ready230 kV substation114 days
Transformers deliveredLong-lead electrical105 days
Hall 1 energisedData halls fit-out60 days
Cooling commissionedCooling plant49 days

Bars scale to 120 days. A reported date is evidence; Capibud's P80 also reflects productivity, remaining risks and crews.

How it works

From the monthly pack to a priced recovery

1Read actualsCost ledgers, progress reports and schedule exports go in as they are. Lines that mix cost roles are held for review.
2UpdateEarned value is blended with a reference-class prior, so one good or bad month does not swing the forecast.
3SimulateRemaining risks, interfaces between units and shared factors are simulated together; crew ceilings and calendar windows are applied.
4Price optionsRecovery options are re-run in the engine and shown with their cost, their effect on P80 finish and their effect on value.
5RouteChange orders and recovery plans go through the authority matrix; approval applies the change, which can be undone.

What it connects to

Recovery money comes from the same envelope

A recovery plan is a capital decision. In the committee it competes with new projects and capex lines, and it often wins: protecting a committed programme is cheap value.

Committee

Recovery as a candidate

Extra crews or shifts are pooled with every other use of capital.

The capital committee
Evaluate

Back to the sanction

Overruns feed the reference class used for the next sanction.

Evaluate
Brain

Drift caught early

New actuals or a contractor's listed peer falling trigger a priced proposal.

The brain
Record

Every change order

Who approved what, on which forecast, is kept in the hash-chained log.

The record

Honest limits

What Execute does not do

Execute is a forecasting and decision layer. It does not run the job site or replace your planning tools.

  • It is not a scheduling tool. Critical-path networks stay in your planning software; Capibud reads their exports and ranges the result.
  • Schedules arrive as exports. Capibud works with what P6, MS Project and your ERP export today (XER, XML, Excel); live connectors are rolling out.
  • Garbage in, ranges out. If progress is over-reported, the forecast inherits it. Capibud flags inconsistencies; it cannot measure the site.
  • Productivity windows are inputs. Monsoons, festival leave and turnaround draws on crews are modelled as you describe them, labelled as estimates.

Bring us the project that keeps slipping.

A Decision Sprint can take one recovery plan from your monthly reports to a priced, routed decision in six weeks.

Talk to us →