- Home
- Case studies
- Data-centre developer
What to build, then keeping phase 1 on track.
Meridian Infrastructure is a synthetic developer on the US Gulf Coast with $2.6bn to deploy and one 600 MW grid interconnect. This case follows the same workspace through two decisions: which projects to build, and what to do when the campus's first phase starts to slip.
The situation
Three good projects and one connection to the grid
The developer holds a queue position for 600 MW at its substation and has $2.6bn. Three candidates are on the table: a 200 MW hyperscale campus for an anchor tenant ($2.0bn), 400 MW of battery storage earning merchant arbitrage and capacity value ($520M) and a 250 MW solar project with a 15-year power purchase agreement ($310M). The hurdle is 9%.
The campus's value depends on lease rates through the AI cycle. The scenarios include a recession with a pause in AI capital spending, a demand air pocket in which hyperscalers pause and lease rates reset lower, and a period of high energy prices. All three projects compete for the same interconnect.
What Capibud did
One workspace from option choice to monthly review
- Built each option from a research model. Margins were calibrated to industry-typical returns and left editable, with capex, schedule and execution risk on shared factors including an AI and data-centre demand cycle.
- Solved the portfolio under the interconnect. The optimiser chose what to build within the budget and the 600 MW constraint for the best expected NPV with a penalty on the bad year, and scored the usual ranked lists on the same scenarios.
- Carried the sanction into construction. Phase 1 of the campus was split into six packages: shell and core, long-lead electrical, a 230 kV substation, cooling plant, backup generation and the fit-out of three data halls.
- Ran the monthly review. At the September 2026 data date, actuals were blended with a reference-class prior, the remaining risks simulated on 2,000 scenarios, and contractor dates checked against Capibud's P80.
- Applied crews and windows. Shared electrical crews were capped at a 550-head site ceiling, with the year-end shutdown and summer heat derating outdoor work.
Results: what to build
Build the campus and the solar; leave $290M unspent
| Method | Selection | E[NPV] | P10 | Bad year | Interconnect |
|---|---|---|---|---|---|
| Capibud | Campus + solar | $394M | $91M | −$91M | 510 / 600 MW |
| Rank by NPV or IRR | Campus + storage | $220M | −$102M | −$304M | 660 / 600 MW |
| Everything above hurdle | All three | n/a | n/a | n/a | 910 MW · $2.8bn |
Illustrative demo — not client data. One seeded engine run. Ranked methods are scored as their projects would run under the real interconnect.
The recommendation has an expected NPV of $394M on $2.31bn of capex, a P10 of $91M and a 5% chance of a negative portfolio NPV. The remaining 90 MW of interconnect is real but useless: the next project in line needs 400 MW. A 10% larger budget would buy nothing that clears the risk-adjusted bar, so $290M stays unspent on purpose.
The campus itself is the risky part: a 7% chance of destroying value on its own, a P10 of $46M and a P50 IRR of 9.9% against the 9% hurdle. Execution slippage costs about $116M across the recommended pair, almost all of it overrun on the campus, whose P80 commercial operation date is April 2030 against a July 2029 plan.
Results: phase 1
Two packages to escalate, and one shift to add
| Package | Budget | P80 cost | P80 finishvs target | Verdict |
|---|---|---|---|---|
| Shell and core | $176M | $187M | Oct 2026 · Sep 2026 | Proceed |
| Long-lead electrical | $228M | $257M | Feb 2027 · Dec 2026 | Recover |
| 230 kV substation | $106M | $120M | Aug 2027 · Mar 2027 | Recover |
| Cooling plant | $150M | $177M | Mar 2027 · Jan 2027 | Escalate |
| Backup generation | $96M | $98M | Jan 2027 · Dec 2026 | Proceed |
| Data halls 1–3 fit-out | $325M | $392M | Feb 2028 · Aug 2027 | Escalate |
Illustrative demo — not client data. Budgets at award; package P80s do not sum to the programme P80.
Programme budget authority is $1,185M. The P80 estimate at completion is $1,218M, and only 42% of scenarios finish within authority. CPI is 0.96 and SPI 0.95. Remaining contingency of $89M covers 73% of the P80 need; five pending change orders worth $43M would use almost half of it if granted.
The finish is driven by the data halls
The fit-out's P80 finish is February 2028, 183 days beyond the August 2027 target, at about $520,000 a day of delay. Crews on the package are at 79% of what the work in hand needs (388 on site against 489) and time-based SPI is 0.85. Capibud's first suggested recovery is a second shift on the fit-out, to be priced and previewed against the crew ceiling before anyone commits.
Bars scale to 120 days. Shared electrical crews also add about 10 days at P80 to the substation.
What it missed and limits
A synthetic workspace, used to show the mechanics
- Margins are assumptions. Each option's margin is calibrated to an industry-typical return and is editable. The ranking between storage and solar is sensitive to it.
- Execution history is generated. Budgets, progress, contractor reports and change orders are synthetic; they show how the review works, not how real campuses perform.
- One run. Figures come from one seeded engine run and move when the synthetic history is regenerated.
- Interconnect is simplified. The constraint is one hard MW limit; real queue positions carry their own timing and upgrade-cost risk.
What this means for you
Lumpy constraints beat ranked lists
Constraints first
Where projects share an interconnect, a plot or a supplier, the best list can be unbuildable. Solve the portfolio, not the ranking.
Unspent can be right
When the next unit is lumpy, holding money back may be the highest-value choice. The plan should say so.
Same book in construction
The sanction range becomes the baseline. Monthly actuals show early whether the case is holding.
Related
Use cases and industries in this case
This case uses Evaluate and Execute. The data-centre, storage and solar packs supply its baselines.
Evaluate: sanction and stage-gates
Options, sizes and timing on shared scenarios.
Read the guideExecute: projects in construction
P80 cost and finish from actuals, recovery priced in money.
Read the guideAn infrastructure investor: the owner's view
Construction assets, including a data-centre campus, looked through from an infrastructure programme.
Read the caseBring us the campus you are building.
A Decision Sprint can take one sanction or one recovery plan from your files to a routed decision in six weeks.