Industry brief · Power & digital
Nuclear powerlarge LWR/PHWR, SMRs, restarts and life extensions
Firm zero-carbon baseload from large light-water (AP1000, EPR, VVER, APR1400) and Indian PHWR-700 reactors, fast breeders (PFBR), small modular reactors (BWRX-300, NuScale, Natrium, Bharat Small Reactors) plus restarts and uprates of existing units. The asset class has the worst cost/schedule overrun record in the power sector (mean ~117%), so FOAK risk, regulatory licensing, heavy-forging supply and financing structure (RAB, CfD, government equity, hyperscaler PPAs) dominate capital outcomes.
Pack v1.0.0 · updated 5 Oct 2026 · 19 cited sources · 13 parameters · 10 swing factors.
At a glance
Pack defaults with their low–high range. Overruns are sector means as a share of the original budget or schedule. All parameters and sources
Sub-industries
Capex intensity ranges by configuration. The unit changes with the asset, so compare within a row, not across rows.
| Sub-industry | Capex intensity | Notes |
|---|---|---|
| Large LWR (AP1000, EPR/EPR2, APR1400, VVER-1200)1,000-1,650 MWe Gen III+ units built in pairs/fleets; US Vogtle 3&4, France Flamanville 3 and EPR2, UK Hinkley Point C / Sizewell C, Czech Dukovany II (KHNP), India Kudankulam 3-6 (VVER). | 2,100–17,600USD per kW | Range spans India VVER (~Rs 20-25 crore/MW = USD 2,100-2,600/kW, Kudankulam 3-6) to US Vogtle-based USD 12,300-17,570/kW (Lazard LCOE+ 2026). EIA AEO2026 LWR overnight USD 8,255/kW (2025$). |
| Indian PHWR-700 fleet modeIndigenous 700 MWe pressurised heavy water reactors built in fleet mode by NPCIL (Kakrapar 3&4, RAPP 7&8, Gorakhpur, Kaiga 5&6, Mahi Banswara, Chutka). | 1,500–2,100USD per kW | Fleet of 10 x 700 MW sanctioned 2017 at ~Rs 1.05 lakh crore (~Rs 15 crore/MW); Mahi Banswara 4x700 MW ~Rs 42,000 crore. USD at INR 95.8 - estimate. |
| Small modular reactors (LW-SMR 50-470 MWe)Factory-fabricated light-water SMRs: GE Vernova Hitachi BWRX-300 (OPG Darlington, TVA Clinch River), NuScale/ENTRA1 77 MWe modules, Rolls-Royce SMR 470 MWe, Holtec SMR-300, India's BSR-220 and BSMR-200. | 8,000–20,000USD per kW | OPG Darlington FID May 2025: C$7.7bn for unit 1 (incl. shared infrastructure) and C$13.2bn for units 2-4 (~USD 12,000-18,000/kW). EIA AEO2026 SMR USD 9,831/kW. NuScale UAMPS cancelled at USD 9.3bn for 462 MWe (~USD 20,000/kW). |
| Advanced non-LWR (sodium-fast, HTGR, molten salt, microreactors)TerraPower Natrium (345 MWe SFR + salt storage), X-energy Xe-100 (Dow, Amazon), Kairos Hermes (Google), Oklo Aurora, India PFBR 500 MWe (first criticality Apr-2026). | 10,000–25,000USD per kW | FOAK; PFBR cost rose to Rs 8,181 crore for 500 MWe (~USD 1,700/kW nominal, multi-decade). Western FOAK estimates are estimate-grade. |
| Restarts, uprates and long-term operationReturning shut units to service (Palisades, Crane/TMI-1, Duane Arnold), power uprates and 60-80 year licence extensions incl. steam-generator and turbine replacement. | 500–2,200USD per kW | Crane (835 MW) restart ~USD 1.6bn (~USD 1,900/kW); Palisades restart backed by USD 1.52bn DOE loan; uprates USD 1,000-2,000/kW - estimate. |
Value chain
Inputs
- uranium (U3O8)
- conversion and enrichment (SWU), HALEU for advanced reactors
- fuel fabrication
- heavy forgings (RPV, steam generators)
- nuclear-grade concrete and rebar
- safety-class valves, pumps, I&C
- turbine-generator islands
- licensed workforce and QA (NQA-1 / AERB)
Process
- site permit / ESP and environmental review
- construction licence (NRC Part 50/52/53, AERB, ONR, ASN)
- nuclear island civil and module construction
- conventional island and BOP
- cold/hot functional testing
- fuel load and first criticality
- power ascension and commercial operation
- operations, refuelling outages, spent fuel management
Outputs
- baseload electricity (90%+ capacity factor)
- firm capacity and clean-energy attributes
- process heat/steam (industrial, desalination, hydrogen)
- isotopes
- spent fuel and decommissioning liabilities
Parameters
13 parameters: 9 sourced, 4 informed estimates. The bar shows the low–high range with the default marked; estimates are labelled and never presented as observed data.
| Parameter | Default & range | Evidence | Source |
|---|---|---|---|
| Capex intensity(global blended; India PHWR ~1,600, US/EU 8,000-17,000) | 9,000 USD/kWrange 1,500–17,600 | sourcedas of 5 Oct 2026 | eia.gov lazard.com |
| Construction months | 96 monthsrange 60–216 | sourcedas of 5 Oct 2026 | lazard.com en.wikipedia.org |
| Cost overrun mean | 117%range 20%–300% | sourcedas of 5 Oct 2026 | doi.org |
| Schedule overrun mean | 90%range 20%–250% | sourcedas of 5 Oct 2026 | en.wikipedia.org en.wikipedia.org |
| Asset life (years) | 60 yearsrange 40–80 | sourcedas of 5 Oct 2026 | lazard.com |
| WACC | 8%range 5%–11% | estimateas of 5 Oct 2026 | RAB/government-backed 5-7%; merchant/FOAK 9-11% |
| Typical IRR(equity) | 10%range 7%–14% | estimateas of 5 Oct 2026 | regulated utility ROE ~9.5-10.5%; Sizewell C RAB allowed return ~low double digits |
| Utilization(capacity factor) | 90%range 75%–95% | sourcedas of 5 Oct 2026 | lazard.com |
| Opex % of revenue | 40%range 30%–55% | estimateas of 5 Oct 2026 | fixed O&M USD 136-158/kW-yr + fuel ~USD 6-9/MWh vs USD 80-100/MWh revenue |
| EBITDA margin | 50%range 35%–65% | estimateas of 5 Oct 2026 | Constellation/NPCIL operating margins |
| Fixed O&M (USD per kW-yr) | 150 USD/kW-yrrange 107–165 | sourcedas of 5 Oct 2026 | eia.gov |
| Fuel cost (USD per MMBtu) | 0.85 USD/MMBturange 0.64–1.06 | sourcedas of 5 Oct 2026 | lazard.com |
| LCOE (USD per MWh)(US new-build, unsubsidised) | 215 USD/MWhrange 175–255 | sourcedas of 5 Oct 2026 | lazard.com |
What moves value
Sorted by expected cost (probability × cost impact). Impacts are typical values for the sector; each one is driven by the shared factors listed, which is how one shock reaches several projects at once.
Market signals
What moves the case
Key variables with their typical range and what they hit in the model.
| Variable | Typical range | Affects |
|---|---|---|
| Overnight capital costCapital is ~70-80% of nuclear LCOE; +10% capex ~ +7-8% LCOE. | 2,000–18,000USD/kW | Capex |
| Construction duration (FCD to COD)At 8% WACC each extra year of build adds ~8-10% to all-in cost via IDC. | 60–180months | Capex, Financing |
| Uranium U3O8 priceFuel ~USD 6-9/MWh; U3O8 is ~40% of fuel cost, so +USD 20/lb ~ +USD 1/MWh. FRED USD 69/lb (Jul-2026), UxC futures ~USD 90. | 40–120USD/lb | Opex |
| Enrichment (SWU) priceRussian supply bans (US from 2028) tightened SWU; Russia holds ~40% of global enrichment capacity. | 100–250USD/SWU | Opex |
| Capacity factorUS fleet ~90-93%; Indian fleet lower for older PHWRs; each 1 pt ~1.1% revenue. | 75%–95% | Revenue |
| Long-term PPA / CfD strike priceHyperscaler nuclear PPAs reported at ~USD 80-100+/MWh; HPC CfD GBP 92.50/MWh (2012 prices). | 60–160USD/MWh | Revenue, Margin |
| US 10-year TreasuryMost rate-sensitive power asset: +100 bp WACC ~ +12-15% LCOE. | 3–6percent | Financing |
| India 10-year G-secNPCIL debt/equity 70:30 with budgetary equity; tariffs set by DAE. | 6–8percent | Financing |
Show 4 more variables
| Variable | Typical range | Affects |
|---|---|---|
| Steel mill products PPIRebar/liner/structural modules; +23% y/y Aug-2026. | 180–420index | Capex |
| Construction materials PPICivil works ~25-30% of nuclear island cost. | 230–400index | Capex |
| US construction hourly earningsLabour is ~40-50% of US nuclear direct cost; productivity matters more than rate. | 35–50USD/h | Capex |
| US average retail electricity priceSupports restarts/uprates economics and PPA pricing; +46% since 2020. | 0.13–0.22USD/kWh | Revenue |
Price feeds (13)
| Series | Source / id | Unit | Frequency |
|---|---|---|---|
| Global price of Uranium | PURANUSDMFRED | USD/lb | monthly |
| UxC U3O8 futures | UX=FYahoo | USD/lb | daily |
| Global X Uranium ETF | URAYahoo | USD | daily |
| VanEck Uranium & Nuclear ETF | NLRYahoo | USD | daily |
| PPI: Steel mill products | WPU1017FRED | index | monthly |
| PPI: Construction materials | WPUSI012011FRED | index | monthly |
| PPI: Turbines and turbine generator sets | PCU333611333611FRED | index | monthly |
| PPI: Power and specialty transformers | PCU335311335311FRED | index | monthly |
Show 5 more feeds
| Series | Source / id | Unit | Frequency |
|---|---|---|---|
| Average hourly earnings, construction | CES2000000003FRED | USD/h | monthly |
| Average price: electricity per kWh, US city average | APU000072610FRED | USD/kWh | monthly |
| US 10-year Treasury yield | DGS10FRED | percent | daily |
| India 10-year government bond yield | INDIRLTLT01STMFRED | percent | monthly |
| Germany 10-year Bund yield | IRLTLT01DEM156NFRED | percent | monthly |
Listed tickers (22)
Market context only: these prices tend to react first when a driver moves. Named for context; no affiliation.
Operators · 8
- NTPC.NS NTPC (ASHVINI JV with NPCIL) NSE · IN
- CEG Constellation Energy NASDAQ · US
- SO Southern Company (Vogtle) NYSE · US
- VST Vistra (Comanche Peak, Beaver Valley) NYSE · US
- OKLO Oklo NYSE · US
- CEZ.PR CEZ (Dukovany II) PSE · EU
- FORTUM.HE Fortum Nasdaq Helsinki · EU
- ENGI.PA Engie (Belgian fleet LTO) Euronext Paris · EU
Suppliers · 13
- LT.NS Larsen & Toubro (heavy forgings, nuclear EPC) NSE · IN
- BHEL.NS BHEL (PHWR turbine islands, SGs) NSE · IN
- WALCHANNAG.NS Walchandnagar Industries NSE · IN
- MTARTECH.NS MTAR Technologies NSE · IN
- HCC.NS Hindustan Construction Co. NSE · IN
- CCJ Cameco (49% Westinghouse) NYSE · US
- BWXT BWX Technologies NYSE · US
- GEV GE Vernova (GE Vernova Hitachi BWRX-300) NYSE · US
- LEU Centrus Energy (HALEU/LEU) NYSE · US
- SMR NuScale Power NYSE · US
- RR.L Rolls-Royce (Rolls-Royce SMR) LSE · EU
- KAP.IL Kazatomprom LSE IOB · APAC
- 034020.KS Doosan Enerbility KRX · APAC
Proxys · 1
- URA Global X Uranium ETF NYSE Arca · US
Trends and research findings
Trends
- Construction pipeline at multi-decade high2025-2035
63 reactors (>70 GW) under construction globally, among the highest since 1990; nuclear investment >USD 70bn in 2025.
- Hyperscaler-led nuclear demand2025-2035
Up to 25 GW of SMR plans tied largely to data centres; restarts (Crane, Palisades, Duane Arnold) and long PPAs re-rate existing fleets.
- India opens nuclear to private capital2026-2047
Budget FY26 set a 100 GW-by-2047 goal and amendments to the Atomic Energy and Civil Liability Acts (SHANTI Act); Nuclear Energy Mission funds Bharat Small Reactors.
- SMR cost reality check2025-2040
Darlington BWRX-300 unit 1 at C$7.7bn and NuScale UAMPS cancellation (USD 3.6bn to 9.3bn) show FOAK SMRs above USD 10,000/kW; IEA sees US/EU SMR cost of USD 4,500/kW only by 2040 in an accelerated case.
- Europe recommits with RAB/state models2025-2040
Sizewell C FID (Jul-2025, ~GBP 38bn, UK govt 44.9%), EPR2 programme, Dukovany II; but HPC now ~GBP 35bn in 2015 prices (~GBP 48bn 2026 prices).
- Fuel-cycle security2025-2032
Russia holds ~40% of global enrichment capacity; >99% of enrichment sits with four suppliers - driving new Western SWU and HALEU investment.
Research findings
- Vogtle 3&4 cost escalation
Certified cost of USD 14bn (2017) rose to ~USD 34bn by 2023; Georgia Power's 45.7% share implies ~USD 23.8bn capitalised construction cost plus USD 3.5bn financing.
- Flamanville 3
Original EUR 3.3bn / 54-month build; EDF estimate rose to EUR 12.4-13.2bn; grid connection Dec-2024 and full power Dec-2025.
- Hinkley Point C
Cost estimate ~GBP 35bn (2015 prices), almost double the approval estimate, with unit 1 now projected for 2030.
- Lazard LCOE+ 2026 nuclear
US new nuclear capex USD 12,300-17,570/kW; LCOE USD 175-255/MWh unsubsidised, USD 129-228/MWh with PTC; 84-month construction; 60-80 year life.
- EIA AEO2026
LWR overnight USD 8,255/kW (6-yr lead), SMR USD 9,831/kW with 1.10 technological-optimism factor; fixed O&M USD 163/kW-yr.
- Indian costs
Kudankulam 3&4 estimated at Rs 200 million/MW and 5&6 at Rs 250 million/MW; PFBR cost rose to Rs 8,181 crore before first criticality in Apr-2026.
- Overrun distribution
Nuclear has the highest mean cost overrun (117%) of any electricity asset class in a 401-project sample.
KPIs, regions and who builds
KPIs the pack tracks
Regional notes
| India | 8.88 GW operating (25 reactors), 8.7 GW under construction; PHWR-700 fleet mode keeps costs ~Rs 15 crore/MW but schedules slip; PFBR critical Apr-2026; Kudankulam 5 ~Dec-2026, unit 6 ~Sep-2027. SHANTI Act and Nuclear Energy Mission open BSR-220/SMR to private developers and NTPC; liability and fuel supply (NSG, imported uranium) remain key. |
|---|---|
| United States | Executive orders (May-2025) target 400 GW by 2050 and new large reactors under construction by 2030; restarts (Palisades, Crane), uprates and hyperscaler PPAs lead near-term. 45U/45Y/48E credits preserved for nuclear under OBBBA. Vogtle lessons: complete design before construction, fixed vendor accountability, experienced constructor, realistic labour productivity. |
| Europe | France EPR2 (6 units), UK HPC/Sizewell C/RR SMR, Czech Dukovany II, Poland AP1000 (Lubiatowo), Sweden new build; financing via RAB, CfD and state equity. EU taxonomy includes nuclear; Germany remains exited. |
| Middle East | UAE Barakah (5.6 GW, KEPCO) is the on-time benchmark; Saudi Arabia tendering first plant; Egypt El Dabaa (VVER-1200) under construction. |
Who builds and operates
Named for context; no affiliation. These are public market participants drawn from the research behind the pack. They are not Capibud clients or partners.
Operators · 14
- NPCIL (Nuclear Power Corporation of India) Operates India's 25 reactors (8,880 MW as of Apr-2025); 11 reactors (8,700 MW) under construction incl. Kudankulam 3-6, RAPP-8, Gorakhpur; fleet-mode PHWR-700.
- BHAVINI 500 MWe PFBR achieved first criticality 6-Apr-2026 after ~two decades; cost Rs 8,181 crore.
- ASHVINI (NPCIL 51% / NTPC 49%) JV building Mahi Banswara 4x700 MW (~Rs 42,000 crore); NTPC targets ~30 GW nuclear by 2047.
- Indian private entrants (Tata Power, Adani, Reliance, JSW, Hindalco) Positioned for Bharat Small Reactors and private participation enabled by the SHANTI Act (Dec-2025) amendments to Atomic Energy and liability laws.
- Constellation Energy Largest US nuclear fleet (~22 GW+ after Calpine); Crane (TMI-1) restart for Microsoft (2027), Meta Clinton PPA, uprates.
- Southern Company / Georgia Power Vogtle 3&4 AP1000s (COD Jul-2023 / Apr-2024); total project cost ~USD 34bn+.
- Tennessee Valley Authority Clinch River BWRX-300 construction permit application; first US SMR fleet candidate.
- Holtec International Palisades restart (status returned to operational Aug-2025) and SMR-300 twin units planned at the site.
- EDF 56-reactor French fleet; Flamanville 3 EPR (grid Dec-2024, full power Dec-2025); EPR2 programme of 6 units; Hinkley Point C (unit 1 ~2030).
- Sizewell C Ltd (UK Govt 44.9%, La Caisse, Centrica, EDF, Amber) FID 22-Jul-2025 under RAB model; ~GBP 38bn cost estimate.
- CEZ / EDU II Dukovany II 2 x APR1000 awarded to KHNP (contract 2025).
- TVO / Fortum / Vattenfall OL3 EPR in regular operation since Apr-2023 after 18-year build; Vattenfall Ringhals SMR plans.
- Ontario Power Generation Darlington New Nuclear: 4 x BWRX-300, unit 1 FID May-2025 (C$7.7bn), first G7 SMR (North America).
- ENEC / Nawah (Barakah) 4 x APR1400 (5.6 GW) operating; benchmark for on-schedule Korean delivery.
Suppliers · 15
- Westinghouse Electric (Brookfield / Cameco) AP1000/AP300; US government partnership (2025) targeting a large AP1000 fleet; Poland, Bulgaria, Ukraine projects.
- EDF / Framatome EPR/EPR2, fuel and heavy components; Jaitapur (6 x EPR) in India under negotiation.
- GE Vernova Hitachi Nuclear Energy BWRX-300 SMR for OPG, TVA, Poland (OSGE).
- KHNP / KEPCO E&C / Doosan Enerbility APR1400/APR1000; Barakah, Dukovany II; Doosan supplies RPVs/SGs incl. for US SMRs.
- Rosatom / Atomstroyexport VVER-1000/1200 for Kudankulam 3-6; also Paks II, Akkuyu, Rooppur.
- Larsen & Toubro (Heavy Engineering, Hazira forging) Steam generators, end-shields, forgings for PHWR/PFBR; major EPC for NPCIL.
- BHEL Turbine islands and steam generators for PHWR-700 fleet.
- Walchandnagar, MTAR, Godrej & Boyce Calandria, fuelling machines, precision assemblies.
- BWX Technologies Naval and commercial components, TRISO fuel, Canadian SG manufacturing for OPG.
- Rolls-Royce SMR 470 MWe SMR selected by Great British Nuclear (2025) and CEZ.
- NuScale Power / ENTRA1 Only NRC-approved SMR design (77 MWe uprate approved 2025); TVA/ENTRA1 6 GW framework.
- Cameco / Kazatomprom / Orano Uranium mining/conversion; Kazatomprom ~20%+ of world mine supply.
- Urenco / Centrus / Orano Enrichment; Russian (Tenex) supply being phased out in US by 2028.
- Bechtel / Fluor / Kiewit Vogtle completion (Bechtel); constructor capacity is a key US bottleneck.
- Curtiss-Wright / Holtec / Mirion Pumps, valves, I&C, spent fuel storage, radiation monitoring.
Customers · 5
- Hyperscalers (Microsoft, Amazon, Google, Meta) Microsoft-Crane 20-yr PPA; Amazon-Talen Susquehanna (~1.9 GW); Meta-Constellation Clinton; Google-Kairos 500 MW; Amazon-X-energy.
- State discoms (India) NPCIL tariffs ~Rs 3-6/kWh set by DAE; payment security under LPS rules.
- Regulated utilities (US/EU) Cost recovery through rates (Georgia PSC) or RAB (UK).
- Energy-intensive industry (steel, aluminium, chemicals) Indian BSR-220 marketed for captive industrial decarbonisation; Dow/X-energy Seadrift.
- Governments / TSOs CfDs (HPC GBP 92.50/MWh 2012$), state equity, loan guarantees (DOE LPO).
Project template
Work breakdown
Share of total duration per step; steps overlap where predecessors allow, as the bars show. O / ML / P are optimistic, most-likely and pessimistic multipliers on each step's duration; the hatched tail is the pessimistic case.
| ID | Step & timing | Share | O / ML / P |
|---|---|---|---|
| A100 | Siting, ESP/site permit and environmental impact assessmentDevelop · factors: Policy | 15% | 0.9 / 1 / 1.6 |
| A110 | Technology selection, vendor contract and financing structure (RAB/CfD/PPA/LPO)Develop · factors: Interest rates, Policy | 10% | 0.9 / 1 / 1.8 |
| A120 | Construction licence (NRC COL/CP, AERB siting/construction consent)Develop · factors: Policy | 15% | 0.85 / 1 / 1.7 |
| A130 | Grid connection and evacuation schemeDevelop · factors: Grid queue | 10% | 0.9 / 1 / 1.5 |
| B100 | Site-specific detailed design (target >80% complete before FCD)Engineer · EPC · factors: Labour | 20% | 0.9 / 1 / 1.5 |
| C100 | Long-lead: RPV, steam generators, pumps, forgingsProcure · OEM · factors: Steel, Electrical equipment | 35% | 0.9 / 1 / 1.6 |
| C110 | Turbine-generator island and GSU transformersProcure · OEM · factors: Electrical equipment, Copper | 25% | 0.9 / 1 / 1.5 |
| C120 | Initial fuel core procurement (U3O8, conversion, SWU, fabrication)Procure · factors: Policy, Gas | 20% | 0.9 / 1 / 1.5 |
| D100 | Site preparation, excavation and basemat (first nuclear concrete)Construct · EPC · factors: Construction materials, Labour | 12% | 0.9 / 1 / 1.5 |
| D110 | Nuclear island: containment, modules, RPV and SG settingConstruct · EPC · factors: Labour, Steel, Construction materials | 40% | 0.9 / 1 / 1.7 |
| D120 | Conventional island and balance of plantConstruct · EPC · factors: Labour, Steel, Copper | 30% | 0.9 / 1 / 1.4 |
| E100 | Cold and hot functional testing, ITAAC closureCommission · EPC · factors: Policy, Labour | 8% | 0.9 / 1 / 1.8 |
| E110 | Fuel load, first criticality and power ascension to CODCommission · factors: Policy, Grid queue | 6% | 0.9 / 1 / 2 |
Cost breakdown
Share of capex by line, with the commodity exposure of each line (the share of that line that moves with the commodity).
Financial template
Revenue model
Long-term regulated/contracted revenue: DAE-notified tariffs (India), rate-base recovery (US regulated), RAB or CfD (UK/EU), or 20-year hyperscaler PPAs; merchant plants earn energy + capacity + clean attributes (US 45U/45Y PTCs).
Margin driver
Capacity factor
Ramp-up
1 year to steady state
How Capibud uses this pack
A pack is a starting position, not a forecast. When a nuclear power decision opens in Capibud, pack v1.0.0 is copied in and pinned to that decision. The 13 parameters, 10 swing factors and templates the committee saw stay attached to the decision record, even after the pack is next refreshed.
Parameter ranges and WBS durations seed the P50, P80 and P90 for capex, schedule and value. Your own estimates, vendor quotes and actuals replace pack defaults line by line, and the record shows which numbers are still defaults.
Each swing factor is wired to shared factors; here the heaviest are labour, policy, steel and electrical equipment. A move in one factor hits every exposed project in the same scenario, which is how the capital committee sees concentration across a book rather than project by project.
The 13 price feeds and 22 listed tickers feed the brain, which watches for drivers moving outside their pack range and drafts the change for a person to review.
Shared factors behind this pack's swing factors
- Labour
- Policy
- Steel
- Electrical equipment
- Interest rates
- Data-centre demand
- Gas
Capex tied to a shared factor
- Labour25%
- Steel19.2%
- Electrical equipment13.2%
- Construction materials12%
- Interest rates11%
- Policy7.9%
- Copper2.4%
Sources
Every link opens the original source in a new tab. Values marked as estimates are informed estimates by the Capibud research team.
- iea.orghttps://www.iea.org/reports/the-path-to-a-new-era-for-nuclear-energy/executive-summary
- iea.orghttps://www.iea.org/reports/world-energy-investment-2025/executive-summary
- eia.govhttps://www.eia.gov/outlooks/aeo/assumptions/pdf/EMM_Assumptions.pdf
- lazard.comhttps://www.lazard.com/media/kcfconhf/lazards-lcoeplus_vf.pdf
- doi.orghttps://doi.org/10.1016/j.erss.2014.07.016
- en.wikipedia.orghttps://en.wikipedia.org/wiki/Vogtle_Electric_Generating_Plant
- en.wikipedia.orghttps://en.wikipedia.org/wiki/Flamanville_Nuclear_Power_Plant
- en.wikipedia.orghttps://en.wikipedia.org/wiki/Hinkley_Point_C_nuclear_power_station
- en.wikipedia.orghttps://en.wikipedia.org/wiki/Sizewell_C_nuclear_power_station
- en.wikipedia.orghttps://en.wikipedia.org/wiki/Olkiluoto_Nuclear_Power_Plant
- en.wikipedia.orghttps://en.wikipedia.org/wiki/BWRX-300
- en.wikipedia.orghttps://en.wikipedia.org/wiki/NuScale_Power
- en.wikipedia.orghttps://en.wikipedia.org/wiki/Nuclear_power_in_India
- en.wikipedia.orghttps://en.wikipedia.org/wiki/Prototype_Fast_Breeder_Reactor
- en.wikipedia.orghttps://en.wikipedia.org/wiki/Kudankulam_Nuclear_Power_Plant
- en.wikipedia.orghttps://en.wikipedia.org/wiki/Palisades_Nuclear_Generating_Station
- en.wikipedia.orghttps://en.wikipedia.org/wiki/Three_Mile_Island_Nuclear_Generating_Station
- npcil.nic.inhttps://npcil.nic.in/
- fred.stlouisfed.orghttps://fred.stlouisfed.org/series/PURANUSDM
Bring us one real decision in nuclear power.
We start it from the Nuclear power pack v1.0.0: 13 parameters, 10 swing factors and the 13-step project template, pinned to your decision.